Home / Engineering, construction and port operations
Service groups 3, 4, 5Engineering, construction and port operations
From survey, design and construction to equipment selection and operations: the technical steps are handled by one team so structure, function and cost fit together.

Group 3
Survey, design and construction of port facilities
Survey, design, verification, project management, supervision and construction, including EPC, through one team.
- Topographic, geotechnical and metocean surveys
- Design of seaport, waterway and utility infrastructure
- Design and cost verification
- Project, quality, schedule and cost management
- Construction supervision and construction works
- EPC packages and other contract forms within VPCC’s capacity

Group 4
Port technology and equipment selection advisory
Choosing handling technology and equipment that fit the structure, function and life-cycle economics of the port.
- Cargo-handling technology options by cargo type
- Selection of cranes, transport equipment and special-purpose equipment
- Conveyor systems, storage areas and process lines
- Throughput, capacity and expandability analysis
- Capital cost, operating cost, maintenance and equipment life-cycle assessment
- Equipment investment options matched to port structures and functions
Related experience (from the contract register)
| Client | Scope | Location | Year |
|---|---|---|---|
| Song Lam Cement JSC | Design and cost verification of the approach trestle, 100,000 DWT berth and a 3,000 t/h loading/unloading conveyor system | Nghe An | 2015 |
| Song Lam Cement JSC | Supervision of the approach trestle, 100,000 DWT berth and installation of the 3,000 t/h conveyor system | Nghe An | 2016 |

Group 5
Port operations organisation and optimisation
Operating models, procedures and layouts for efficient port operations; upgrading and expanding existing ports.
- Operating model studies
- Procedures for vessel reception, cargo handling and delivery
- Layout of berths, yards and equipment
- Dispatching, management and equipment-operation procedures
- Productivity, turnaround time and operating cost assessment
- Upgrading, expansion and optimisation of existing ports
Related experience (from the contract register)
| Client | Scope | Location | Year |
|---|---|---|---|
| Gemadept Dung Quat International Port JSC | Maritime structure protection plan, maintenance procedure and inspection report for Berth 1 | Quang Ngai | 2019 |
| Nam Dinh Vu Port JSC | Maritime safety plan for receiving 40,000 DWT vessels | Hai Phong | 2020 |
| Saigon SSA International Services JV Co., Ltd | Support for extending bulk-cargo operations in 2024 at SP-SSA International Container Port | Ba Ria – Vung Tau | 2023 |
| Vam Co Dong Nai Biochemical JSC | Structural audit of the wharf for vessels up to 50,000 DWT | Dong Nai | 2020 |
Talk to us about your port project
Tell us the type of port, its location and the project stage. VPCC will reply with a suggested way to work together.