Home / Featured projects / Van Phong International Port – Phase 1

Seaports and terminals

Van Phong International Port – Phase 1

Two berths totalling 184 m for vessels up to 50,000 DWT, built by VPCC under an E&C arrangement.

Van Phong International Port – Phase 1

Whole-project scale and key parameters

Berths
02
Total length
184 m
Vessel size
Up to 50,000 DWT
Area
20 ha
Form
E&C

This is the scale of the whole project, not of VPCC’s contract. VPCC’s own scope is set out below.

VPCC role and scope of work

  • Construction of the berth and approach trestle (package XL-01), initial phase of Bac Van Phong General Port (2017)
  • Construction of the revetment combined with a service berth (2018)
  • Construction of Berth 2 and upgrade of Berth 1, phase 1 (2022)
  • Verification of the design to upgrade Berth 1 for 100,000 DWT vessels (2022)

Consulting and technical solutions delivered

  • Construction under an E&C arrangement
  • Design verification for a berth upgrade to larger vessels

Highlights

  • Several phases with the same client from 2017 to 2022

Progress and results

VPCC involvement: 2017 – 2022.

Talk to us about your port project