EPC contractor for Hon La International General Port, with a 1,030 m quay for vessels up to 100,000 DWT.

Hon La International General Port

Whole-project scale and key parameters

Quay length
1,030 m
Vessel size
Up to 100,000 DWT
Area
38.82 ha
Funding
Private

This is the scale of the whole project, not of VPCC’s contract. VPCC’s own scope is set out below.

VPCC role and scope of work

  • 2024: topographic and geotechnical survey; project approval file; 1/500 detailed plan
  • 2024: environmental impact assessment, spoil-disposal file and technical safety file
  • From 2025: EPC contractor – design, procurement of materials and equipment, and construction

Consulting and technical solutions delivered

  • A continuous chain from survey, planning and EIA to EPC through one contractor
  • Design, procurement and construction under one EPC contract

Highlights

  • The clearest example of VPCC’s “from investment idea to construction” model
  • EPC contractor for a port with a 1,030 m quay

Progress and results

Ongoing. EPC works ongoing since 2025.

Talk to us about your port project